Most refurbishment projects start with a set of drawings that someone already has. They may be the original architect's plans, a building control submission from the 1980s, a surveyor's sketch from a previous sale, or a scan of a sheet found in a cupboard. They are cheaper and quicker than a new survey, and they are often the only record of what is hidden behind finishes. They are also often wrong.

This article covers where existing drawings come from, the usual ways they differ from the building, and how to check them before design work relies on them.

[edit] Where existing drawings come from

Common sources include:

Each source tells you what was intended or approved at one point in time. None of them tells you what was actually built, or what has changed since.

[edit] How drawings and buildings drift apart

Differences between a drawing and the building usually come from a handful of causes.

Changes during construction. Walls move, openings are resized and stairs are turned on site, and the drawings are not always updated. "As built" drawings are less common than the title block suggests.

Later alterations. Extensions, knocked-through rooms, new partitions and blocked-up windows are often done without drawings, or with drawings that were never added to the file.

Copying errors. A plan that has been photocopied, faxed or scanned several times may be stretched slightly in one direction. A scan of a print at an unknown scale may not be at the scale written on it.

Drawing conventions. Older drawings may use imperial units, show wall thicknesses that include finishes or exclude them, or leave out non-structural partitions entirely. Design sketches may show sizes written in the rooms rather than dimension lines.

[edit] Checking the drawings

Before relying on existing drawings, it is worth a short site visit with a tape or laser measure. A practical sequence:

  1. Check two or three long overall dimensions, at least one in each direction. If they match, the scale is probably right.
  2. Check the main room sizes against what is written or scaled from the drawing.
  3. Count doors and windows on each elevation and compare positions.
  4. Look for walls that have been added or removed, and for changes in floor level.
  5. Note anything that cannot be seen, such as the direction of floor joists or the position of beams, and treat the drawing as unconfirmed there.

Where the drawings fail these checks badly, a measured survey is usually cheaper than designing on a false base.

[edit] Getting paper drawings into CAD

Once the drawings are known to be reasonable, they usually need to be in CAD before design work can begin. There are three common routes:

  • redrawing by hand over a scanned image, which is slow but lets the drafter interpret unclear areas;
  • raster to vector tracing, which is fast on clean line work but copies stains, hatching and handwriting along with the walls;
  • AI redrawing tools, such as Horezmi, which recognise walls, openings and rooms and draw them as CAD objects. They save time on readable drawings but still need checking against the original.

Whichever route is used, the resulting CAD drawing is only as good as the paper it came from. The checks above apply to the CAD version too.

[edit] Recording what is assumed

A drawing that mixes measured, copied and assumed information should say which is which. A simple note on the drawing, such as "overall dimensions checked on site, internal partitions from 1987 building control drawings, not verified", saves the next person from repeating the same checks or trusting the wrong ones.

[edit] Related articles

Designing Buildings Anywhere

Get the Firefox add-on to access 20,000 definitions direct from any website

Find out more Accept cookies and
don't show me this again